Sprint 1
· 3 min read
From: 2024-10-10
To: 2024-10-13
Scrum Master: Alexandre Cotorobai
Product Owner: Miguel Belchior
Developers: Hugo Correia, Joaquim Rosa, André Oliveira
Sprint Goal
In order to complete the second milestone of our project, it is expectable to conclude the following sprints goals:
- Prepare First Presentation
- Prepare the Initial Presentation Website
- Setup Backlog
- Set the "Definition of Ready"
- Set the "Definition of Done"
- Architecture
| Expected | Quantity |
|---|---|
| Tasks | 12 |
| Epics | 1 |
| Story Points | 7 |
Sprint Backlog
| Taks (SCRUM-*) | Description | Developer | State |
|---|---|---|---|
| SCRUM-8 | Landing Page - Frontend | Joaquim Rosa | Done |
| SCRUM-9 | Landing Page - Testing | Miguel Belchior | Done |
| SCRUM-10 | AWS Cognito Setup | André Oliveira | Done |
| SCRUM-11 | AWS Cognito Setup | André Oliveira | Done |
| SCRUM-12 | API Authentication and Authorization | André Oliveira | Done |
| SCRUM-13 | Landing Page - PWA Support | Joaquim Rosa | Done |
| SCRUM-14 | API Authentication and Authorization | All | Done |
| SCRUM-15 | Landing Page - Little Refacture | Hugo Correia | Done |
| SCRUM-16 | Backend Testing | Miguel Belchior | Done |
| SCRUM-17 | Link Back-end with Front-end | Hugo Correia | Done |
| SCRUM-18 | User Login - Testing | Joaquim Rosa | Done |
| SCRUM-19 | User Registration - Testing | Joaquim Rosa | Done |
Task Status (Completed/Not Completed)
- SCRUM-8: Landing Page - Frontend
- SCRUM-9: Landing Page - Testing
- SCRUM-10: AWS Cognito Setup
- SCRUM-11: AWS Cognito Setup
- SCRUM-12: API Authentication and Authorization
- SCRUM-13: Landing Page - PWA Support
- SCRUM-14: API Authentication and Authorization
- SCRUM-15: Landing Page - Little Refacture
- SCRUM-16: Backend Testing
- SCRUM-17: Link Back-end with Front-end
- SCRUM-18: User Login - Testing
- SCRUM-19: User Registration - Testing
User Stories
| User Stories | Description | Developer | State | Story Points |
|---|---|---|---|---|
| SCRUM-5 | User Registration | All | Done | 3 |
| SCRUM-6 | User Login | All | Done | 3 |
| SCRUM-7 | Landing Page | All | Done | 1 |
Team Velocity: 7
Sprint Review
| Concluded | Quantity |
|---|---|
| Tasks | 12 |
| Epics | 0 |
| Story Points | 7 |
Sprint Retrospective
Despite the short length of this first sprint, we didn’t expect to deliver a large number of features. However, we were able to complete all the tasks we had planned. These include three user stories related to the user authentication epic: user registration, login, and the landing page.
Sprint Burndown Chart